The Gantt chart for the construction of solar power plants | Avenston
When constructing a solar power plant, the critical task is to install photovoltaic modules. If due to unfavorable conditions, for example, due to heavy rains, the installation of photovoltaic modules will be delayed by two days, then the overall term of the project will shift by two days from the expected date of the object commissioning.